Horizontal Flocculators
Overview
Horizontal flocculators promote particle agglomeration through gentle mixing in long, rectangular basins where water flows horizontally through baffled channels or around-the-end configurations. These units create controlled velocity gradients (typically 20-70 sec⁻¹) using mechanical paddles, hydraulic energy, or combination systems to encourage collision and binding of destabilized particles into settleable flocs. Detention times range from 20-45 minutes with floc formation efficiency reaching 85-95% under optimal conditions. The primary trade-off involves balancing adequate mixing energy for particle contact against excessive turbulence that can shear and break formed flocs.
Common Applications
• Conventional Water Treatment Plants (2-50 MGD): Horizontal flocculators serve as the primary flocculation stage between rapid mix and sedimentation basins. They're selected for their excellent hydraulic control and ability to provide the 20-30 minute detention time required for effective floc formation. Upstream connections include flash mixers or in-line blenders; downstream flow feeds directly to clarifiers or settling basins.
• Package Plant Upgrades (0.5-5 MGD): Existing package plants often retrofit horizontal flocculators to replace aging paddle wheel systems. The horizontal configuration fits within existing building constraints while providing superior floc development. These units typically connect between existing chemical feed points and modified clarifier inlets.
• High-Turbidity Surface Water Treatment: Plants treating reservoir or river water with seasonal turbidity spikes (>100 NTU) rely on horizontal flocculators for consistent performance. The compartmentalized design allows staged mixing energy reduction from 100 ft-lb/MG initially to 20 ft-lb/MG in final chambers, optimizing floc strength for varying raw water conditions.
Operator Experience
Daily Operations: Operators monitor floc formation visually through observation ports, adjusting paddle speeds based on jar test results and settled water turbidity. Typical adjustments involve reducing mixing intensity during low-turbidity periods or increasing polymer feed rates. Flow distribution between chambers requires weekly verification using portable flow measurement devices.
Maintenance: Monthly lubrication of gear reducers and bearing assemblies using food-grade lubricants. Quarterly paddle inspection requires confined space entry with proper ventilation and gas monitoring. Annual drive system alignment and vibration analysis prevents catastrophic failures. Maintenance requires millwright skills and overhead crane operation certification.
Troubleshooting: Common failure modes include bearing seizure from inadequate lubrication (3-5 year replacement cycle) and paddle damage from debris impact. Warning signs include excessive vibration, unusual noise, or poor floc formation despite proper chemical dosing. Gear reducer failures typically occur after 8-12 years of continuous operation, requiring planned replacement during scheduled outages.
Major Components
• Mixing Chamber Configuration: Multiple rectangular chambers (typically 3-4 stages) with decreasing mixing intensities. Chamber dimensions range from 20-60 feet length with 8-16 feet depth for municipal applications. Concrete construction with epoxy-coated steel baffles provides 20+ year service life.
• Mechanical Drive Systems: Variable-speed gear reducers (0.5-5 HP) with stainless steel shafts and mixing paddles. Paddle tip speeds decrease from 3 ft/sec in first chamber to 0.5 ft/sec in final stage. Drive selection based on design G-values and chamber geometry.
• Hydraulic Control Structures: Adjustable weirs and baffles control inter-chamber flow distribution and detention time. Stainless steel or fiberglass construction with manual or automated positioning systems. Critical for maintaining plug-flow characteristics and preventing short-circuiting.
• Chemical Feed Integration: Polymer and coagulant injection ports positioned for optimal mixing at each stage. Typically includes dedicated feed lines, mixing nozzles, and sample ports for process monitoring and optimization.
Design Criteria
• Flow Rate: 0.5-50 MGD (0.35-34.7 cfs) with typical velocities of 0.5-1.5 fps through basin length
• Detention Time: 20-45 minutes total, with 3-4 tapered velocity zones of 5-15 minutes each
• Velocity Gradient (G-Value): 20-70 sec⁻¹, decreasing through zones (Zone 1: 50-70 sec⁻¹, Zone 4: 20-35 sec⁻¹)
• Basin Geometry: Length-to-width ratios of 3:1 to 6:1, depths of 10-16 feet for optimal hydraulics
• Baffle Spacing: 2-8 feet between baffles, creating 90-180° turns with headloss of 0.1-0.3 feet per turn
• Power Requirements: 0.5-2.0 hp per MG for mechanical flocculators, 0.1-0.5 feet total headloss for hydraulic systems
• Temperature Range: Design for 32-85°F with viscosity corrections affecting G-value calculations
• Solids Loading: Influent turbidity 5-200 NTU, target floc size 1-3mm for optimal settling
• Overflow Rate: Surface loading rates of 800-1,200 gpd/sf when integrated with sedimentation
Key Design Decisions
• Mechanical vs. Hydraulic Flocculation? Mechanical systems provide precise G-value control (±10%) but require 3-5x higher power consumption (1.5-2.0 hp/MG vs. 0.3-0.5 hp/MG equivalent). Choose mechanical for variable flow plants >10 MGD or when precise control justifies 15-25% higher capital costs. Hydraulic systems suit consistent flow applications with limited maintenance capabilities.
• What detention time and G-value profile? Standard 30-minute detention with 60-50-40-30 sec⁻¹ G-values works for typical 20-100 NTU influent. Extend to 45 minutes for high-turbidity sources >150 NTU or when using polymer aids. Insufficient detention causes poor floc formation; excessive time creates floc breakup and 10-20% higher construction costs.
• Single-stage or multi-stage configuration? Multi-stage (3-4 zones) essential for plants >5 MGD to optimize floc growth. Single-stage acceptable only for small plants <2 MGD with consistent raw water quality. Wrong choice impacts settling efficiency by 15-30% and chemical usage by 10-25%.
• Integration with existing clarifiers? Retrofit applications limited by available space and hydraulic profile. New construction allows optimization of flocculator-clarifier interface for 2-4 fps transition velocities. Poor integration causes floc shear and 20-40% performance degradation.
Specification Section
• Primary: Division 46 23 13 - Packaged Water Treatment Equipment
Submittal + Construction Considerations
• Material/Equipment Verification: Verify paddle materials (fiberglass, aluminum, or stainless steel) meet specifications; Confirm drive system torque ratings and variable speed capabilities; Check concrete mix designs for flocculation basin walls
• Installation Requirements: Precise paddle clearances (typically 6-12 inches from walls/bottom); Proper shaft alignment and bearing installation; Electrical coordination for VFD systems
• Field Challenges: Concrete forming accuracy critical for paddle clearances; Weather protection during drive system installation; Access requirements for future maintenance
• Coordination Issues: Early electrical rough-in coordination for paddle drives; Typical lead times: 16-20 weeks for custom paddle systems
Popular Manufacturers and Models
• WesTech Engineering - Horizontal paddle flocculators with variable-speed drives, widely used in 1-50 MGD plants
• Evoqua Water Technologies - Offers modular horizontal flocculation systems with integrated mixing controls
• Ovivo - Provides horizontal baffle and paddle systems, particularly strong in Canadian municipal market
• Jacobs (formerly CH2M) - Custom-designed concrete horizontal flocculators for larger municipal applications
Alternative Equipment
• Vertical Shaft Flocculators - Better for space-constrained sites, 10-15% higher equipment costs but lower civil costs
• Static Mixers with Serpentine Channels - Eliminate mechanical equipment, preferred for small plants (<2 MGD) with minimal maintenance staff
• Upflow Flocculation Clarifiers - Combine flocculation and settling, cost-effective for new construction but limited retrofit applications
Real-World Tips
Establish relationships with local drive system service providers early - paddle drives require regular maintenance that many plant operators can't perform in-house. Consider oversizing drive systems by 25% to handle seasonal temperature variations and future process changes. Request factory pre-assembly and testing of paddle assemblies to minimize field alignment issues. Specify readily available bearing types to reduce long-term maintenance costs.